Christmas Lights

171207 | For months CC had been doing due diligence towards taking on the harbour | Hayle Town Council minutes

a) Hayle Harbour Update
[155 STANDING AGENDA ITEMS (FOR REPORTING ONLY)]

Councillor Pollard reported that CC was undergoing a peer challenge which had involved six representatives from all over the country coming to Cornwall to see how the council was operating. Hayle had been visited and a positive meeting held, with Councillors Coad and Pollard putting up a strong case for CC to take over the management of the harbour. A video from the Wave Hub had also been shown.

For months CC had been doing due diligence towards taking on the harbour. It had been a greed in January 2017 that CC would buy the harbour and the land around it and provide housing . Due diligence was taking longer than expected but the issue was expected to come before the cabinet in the near future. The portfolio holder had acknowledged that it was still a priority . Councillor Pollard was anxious that CC buy the whole site and develop it for businesses and housing of a good standard and he acknowledged that this was a new direction for CC. In response to a question he added that until CC owned the land it was not able to apply for a grant from the Coastal Communities Fund, although it had already applied for funding for infrastructure, such as roads; the aim of the investment by CC was to attract jobs to the area and having a working estuary was part of this aim.

Book page

TitleCreated
PA19/08727 | Outline planning permission with some matters reserved (access): Construction of up to three dwellings | Land Adj T 3 days 14 hours agoBook page
191018 | Saved in past year- Mill complex ropeworks, Hayle | Cornwall's historic sites which are at risk of being lost forever 3 days 14 hours agoBook page
PA19/08062 | Non material amendment in relation to Construction of 270sqm of floorspace for A1 or A3 use and 3 residential apart 5 days 2 hours agoBook page
PA19/08764 | Submission of details to discharge condition 5 in relation to decision notice PA16/03519 - Hayle Retail SurfaceWate 5 days 2 hours agoBook page
PA19/08759 | Submission of details to discharge condition 4 in relation to decision notice PA16/03519 - Hayle Retail Park CEMP 5 days 2 hours agoBook page
191015 | PA19/08063 | Approved unconditional | Non material amendment to amend conditions 23 and 29 attached to decision notice 5 days 2 hours agoBook page
191001 | Remembering Cunaide, part 2 | Hayle Pump 5 days 8 hours agoBook page
191015 | Cornwall speed camera that catches out the most drivers 5 days 9 hours agoBook page
191015 | Hayle Town Council | Cornwall Community Governance Reviews 5 days 12 hours agoBook page
191015 | Wanted: gentlemen footballers of a generous girth 5 days 12 hours agoBook page
191014 | Badger Cull making TB worse! 1 week 11 hours agoBook page
1985 | A30 Hayle by-pass | Land acquisition and compensation | Total estimated cost including works 1 week 1 day agoBook page