St Austell Bay Resilient Regeneration (StARR) Project

The St Austell Bay Resilient Regeneration (STARR) project aims to reduce flood risk to communities living and working in the St Austell Bay area, particularly in Par and St Blazey. The proposed scheme will bring additional benefits to the area by encouraging investment and making St Austell Bay a better place to work, live and play.

To progress the development of StARR we are working in partnership with:

  • Cornwall Development Company
  • The Environment Agency
  • South West Water
  • The University of Exeter and
  • Westcountry Rivers Trust.

Details of the scheme are available on the STARR Project Plan infographic

This is the STARR Infographic dated July 2018, Released in August

You can find out more about the works to be undertaken on the STARR Project Visualisation

Starr Catchment Visualisation2

For further information please watch the short film below or email StARR@cornwall.gov.uk

View a transcript of this film.


For more information see https://www.cornwall.gov.uk/environment-and-planning/countryside/estuari... resilient-regeneration-starr-project/

 


 

WestCountry Rivers Trust:

The St Austell Bay Resilient Regeneration Project (StaRR) is a £20M flood alleviation and regeneration scheme led by Cornwall County Council.

Funding is being sought for this innovative scheme aiming to work across the whole of the Par and Sandy River Catchments to reduce flood risk to communities living and working in the St Austell Bay area particularly the people of Par and St Blazey. Works will be delivered in partnership between Cornwall County Council, The Environment Agency & Westcountry Rivers Trust, South West Water, the University of Exeter & Cornwall Development Company. Planned implementation is 2017-2020. https://www.cornwall.gov.uk/environment-and-planning/countryside/estuari... bay-%20resilient-regeneration-starr-project/">Find out more here

Westcountry Rivers Trust’s role within the project is to work with local communities in the upper catchment to develop and deliver Natural Flood Management solutions.


St. Austell Bay Resilient Regeneration (StARR) project

Opened 10 Jun 2019

Overview

The St. Austell Bay Resilient Regeneration (STARR) project aims to reduce flood risk to over 800 homes and businesses in Par and St. Blazey.

The scheme will bring additional benefits to the area by encouraging investment and making the area a better place to work, live and play.

We are working in partnership with Cornwall Council, University of Exeter, South West Water and Westcountry Rivers Trust.

Click here to view the image above in more detail: StARR Infographic

Why Par and St. Blazey needs a flood scheme

Many of the homes, businesses and infrastructure of the towns sit in the bed of a former estuary, boats used to sail up and dock at Ponts Mill at the base of Luxulyan Valley. However, over the last few hundred years, the former estuary has become silted up with material bought downstream as a result of tin and clay mining in the upper River Par catchment. The natural river has also been raised up and split in two to drain through the town in the form of the River Par and Treffry Canal which adds to the flood risk.

Par and St. Blazey are affected by 3 different types of flooding:

Surface water flooding - when rainwater doesn’t drain away through the drainage systems or soak into the ground and lies on or flows over the ground

River flooding – when a river or stream exceeds its capacity and overtops its banks. Also known as fluvial flooding.

Tide-locking – when a high tide causes water to back flow. This happens on the Par River, St. Blazey Stream and Polmear Stream.

How the scheme will work

The Par and St. Blazey Flood Defence system is one of the most complex and highly maintained in Cornwall. It is maintained by a number of different organisations and individuals – the Environment Agency, Cornwall Council, South West Water and individual riverside property owners. However, these defences are now quite old and cannot cope with the levels of flooding that are now experienced. The project will repair these existing defences and install more to cope with new demands put on the system to ensure that the chronic flooding problem is now dealt with. We will also be using new innovative natural flood management measures such as rain gardens to store and slow the flow of water.

 

via https://consult.environment-agency.gov.uk/dcis/st-austell-bay-resilient-...

 

St Austell Bay Resilient Regeneration Project (StARR) visualisation
St Austell Bay Resilient Regeneration Project (StARR)

Book page

TitleCreated
240325 | Open letter to all party candidates | sign to help Cornwall Wildlife Trust make difference for Nature at election 1 day 12 hours agoBook page
240310 | Detailed plans for affordable-led housing in Connor Downs 10th March 2 weeks 3 days agoBook page
240310 | Waste collections changes Helston, Penzance, Hayle | second phase:food waste, recycling, rubbish - commences July 2 weeks 3 days agoBook page
240218 | Collapsed North Quay development in Hayle described as a 'sea of despair' 5 weeks 1 day agoBook page
240214 | Hayle North Quay development collapse sees eight companies go bust Work has ground to a halt on the blocks of flats 5 weeks 3 days agoBook page
240220 | Poling works | Grist Lane and Marsh Lane, Angarrack | expected 20 Feb 2024 0830-1630, for one day 7 weeks 2 days agoBook page
231130 | Are you ready for weekly food waste recycling? | Food Waste, Recycling and Rubbish Collection Changes 16 weeks 17 hours agoBook page
230821 | People of Cornwall town 'thrown under bus' over housing plan | direct result of councillors handled Hayle masterplan 31 weeks 1 day agoBook page
230817 | When will new rubbish collection changes start, Cornwall 32 weeks 21 min agoBook page
230809 | Holiday park in Cornwall for emergency housing still empty | Sandbank site purchased Cornwall Council in Jan 2022 32 weeks 5 days agoBook page
230811 | Decision on huge solar farm at Carnhell Green: refused 32 weeks 5 days agoBook page
230809 | Nearest NHS dental practice to Cornwall taking new patients 32 weeks 5 days agoBook page